How PlanWatch calculates what a site with planning is worth
Every approved residential scheme published on PlanWatch is worked through our deterministic residual appraisal engine (appraisal-engine/1.1.0). Every pound on a page traces directly to a sourced ledger row or a labelled default assumption. Last updated 20 Nov 2026.
1. The residual land value sum, step by step
− Build cost (credited single-source £/m² × GIA + externals + abnormals)
− Professional fees (10% typical · 12% high) & contingency (5% standard · 10% basement)
− Planning obligations (scheme-specific S106 + verified CIL schedule or notice)
− Sales, agency & legal costs (3% of GDV)
− Land tax (SDLT in England / LTT in Wales, solved on the bid ceiling)
− Development finance (7% p.a.: land + tax for full holding period, build on 50% average draw)
− Target developer profit (20% of GDV)
= Max Bid ceiling (solved by integer-pence bisection)
Every £ figure displayed in page titles, summaries and meta descriptions is floored to 3 significant figures (and 2 significant figures at narrow title rungs) so a max bid is never rounded up or overstated. When even free land cannot hit the 20% target profit, we state that the sum does not stack and publish the negative residual land value rather than clamping to £0.
2. Default assumptions table
Where planning documents do not state a project-specific figure, PlanWatch applies the following dated defaults and labels every one as an assumption in the workings ledger.
| Assumption | Default | Basis & source |
|---|---|---|
| Target developer profit on GDV | 20% | Owner decision 2 (2026-11-14): 20% profit on GDV is the default target |
| Development finance rate | 7% p.a. | Owner decision 2 (2026-11-14): finance at 7% a year; shown beside Bank Rate as dated context, not a live rate (shown beside Bank of England Bank Rate: 4.0% as of Nov 2026). |
| Professional fees | 10% typical · 12% high | 10% from GLA LPVS Phase 1 (Jul 2026, para 4.107) and Croydon CIL VS (Mar 2024, para 4.18); 12% PlanWatch high-scenario assumption. |
| Construction contingency | 5% standard · 10% basement | 5% from GLA LPVS Phase 1 (para 4.108), applied to construction excl. fees; 10% where a basement is proposed. |
| Sales, agency & legal costs | 3% of GDV | Owner decision 2 (2026-11-14): about 3% sales costs |
| Programme & finance draw | 12m build · 22m land | Land and land tax financed across 22 months (4 pre-start + 12 build + 6 sale); build financed on a 50% average draw. |
| Land tax (SDLT / LTT) | Non-residential default | Effective-dated HMRC SDLT (England, Apr 2025 bands) and WRA LTT (Wales, Dec 2024 bands) tables; 6+ dwellings in one transaction take non-residential bands. |
| Build-cost indexing (optional) | ONS OPI (2026-09) | Source: Office for National Statistics, Construction Output Price Indices (Housing, new work, 2015=100), licensed under the Open Government Licence v3.0; applied by PlanWatch. |
3. Quality gates & privacy rules (G1–G11)
We do not publish thin, guessed or unverified pages. A site only receives its own address URL when it passes all eleven gates:
- 5+ net new homes only (G2 & G10): Full addresses are published only for schemes of 5 or more net new homes, with the count confirmed against the council's decision notice or officer report by a reviewed parser. Smaller 1–4 home approvals appear on council hubs by postcode district only.
- Live decision & coverage (G1, G4, G11): Granted, allowed on appeal, or resolved to grant (clearly labelled), decided within 24 months, in an English authority whose decision harvest is healthy with ≥60% coverage.
- Comparable evidence & confidence (G6, G7): Either ≥5 HM Land Registry sales joined to EPC floor area by UPRN (never using EPC addresses), or ≥8 same-type HPI-indexed sales against the confirmed unit mix with NDSS minimum floor areas, within a ±25% confidence band.
- Verified site fact (G8): At least one verbatim quote from the council's officer report or decision notice (with document link and paragraph), or a scheme-specific S106/CIL obligation from the scheme's own documents.
- Privacy & clean record (G9): No personal names in addresses, no health or disability details, no reference collisions, and rapid 410 takedown on privacy grounds via our error-report form.
4. Engine version & change log
| Date | Version | Change |
|---|---|---|
| 2026-11-14 | appraisal-engine/1.1.0 | Published residual appraisal methodology with bisection over integer pence, April 2025 England SDLT & December 2024 Wales LTT tables, non-viable negative RLV handling, and single-source viability study credits. |
| 2026-11-14 | seo-gates/v5 | Enforced 5+ home address threshold, G1–G11 / H1–H5 index gates with hysteresis, transitional G6 comps rule, and OGL v3.0 data-source register. |
Authored by Ben Thompson (PlanWatch). No external surveyor or legal endorsement is implied.