On this page 13 sections
- 01Short answer: the rules at a glance (England)
- 02Full permission: reading the time-limit condition
- 03Outline permission and reserved matters
- 04Listed building consent
- 05Prior approvals and permitted development
- 06What counts as starting work?
- 07Can an expired permission be extended or renewed?
- 08Completion notices: stalled developments
- 09Does planning permission go with the house?
- 10What neighbours and buyers should check
- 11Wales, Scotland and Northern Ireland
- 12Frequently Asked Questions
- 13The point to remember
In England planning permission lasts 3 years from the date it was granted unless the decision notice says otherwise, and the test is whether the development was begun in time, not whether it was finished. The rule is in section 91 of the Town and Country Planning Act 1990: the applicable period in England is three years, and the council may direct a longer or shorter one. The time-limit condition on your decision notice is the thing to read. This guide covers England, as at October 2026.
Short answer: the rules at a glance (England)
| Permission | Time limit | Law |
|---|---|---|
| Full or householder permission | Begin development within 3 years of the grant, or the period the council directed | s91(1), (5)(a) |
| Outline permission | Apply for reserved matters within 3 years; begin development within 2 years of the final reserved matters approval | s92(2) |
| Listed building consent | Begin works within 3 years of the grant, or the period the authority directs | LBCA 1990 s18(1) |
| Prior approval (additional storeys, commercial to residential, agricultural conversions) | Complete within 3 years of the prior approval | GPDO Class AA.2(3)(c), Class MA.2(5), Class Q.2(4) |
The Planning Practice Guidance confirms the 3-year default and that "such other period (whether longer or shorter)" can be imposed (PPG Use of planning conditions 21a-027). If a permission is granted without a time-limit condition, the statutory one is deemed to apply (s91(3)).
Full permission: reading the time-limit condition
Every grant of planning permission carries a condition that the development "must be begun not later than the expiration of" the applicable period, "beginning with the date on which the permission is granted" (s91(1)). Note the starting date: the date of the decision, not the application date or the date you receive the decision notice.
On the decision notice, look for wording like "The development hereby permitted shall begin not later than three years from the date of this permission". If the notice sets a different period, that governs, because the council may direct "such other period (whether longer or shorter)" if it considers it appropriate having regard to the development plan and other material considerations (s91(1)(b), (2)). Do not rely on a portal summary, which may show the validated, target or decision date but not the expiry.
Two exceptions are worth knowing:
- Legal challenges extend the period in England. Under the rules in force since 18 February 2026, if a court gives permission to bring a challenge to the validity of the grant, the period is extended by one year, and by further periods if permission is given to appeal to the Court of Appeal (one year) or the Supreme Court (two years) (s91(3B)–(3BB), substituted by the Planning and Infrastructure Act 2025 s56). A simpler one-year extension for legal challenges had applied in England before that, and the 2025 Act restructured it and preserved extensions that had already arisen (s56(5)–(6) of the 2025 Act). It does not revive a period that had already expired.
- Section 91 does not apply to permissions granted by a development order, to permissions for a limited period, to permissions granted for development already carried out, or to outline permissions (s91(4)).
Outline permission and reserved matters
Outline permission is granted with some matters reserved for later approval. In England it must be granted subject to conditions that (a) an application for any reserved matter be made "not later than the expiration of three years beginning with the date of the grant", and (b) development must begin "not later than the expiration of two years from the final approval of the reserved matters" or, if approved on different dates, the last of them (s92(2)). The council may substitute other periods, and may set separate periods for separate parts of the development (s92(4)–(5)).
Court challenges also extend outline timetables in England: a new section 92A adds one year when a court gives permission to bring proceedings, with further extensions on appeal (Planning and Infrastructure Act 2025 s56(3)). For how reserved matters work, see our guide to reserved matters planning.
Listed building consent
Listed building consent must be granted subject to a condition that works "must be begun not later than the expiration of" three years from the grant, or another period the authority directs (LBCA 1990 s18(1)). The same legal-challenge extensions apply (s18(2B)–(2BB)). Consent to retain works already carried out is exempt (s18(3)). Doing works to a listed building without consent is a criminal offence (s9); see planning permission for listed buildings.
Prior approvals and permitted development
Permitted development is planning permission granted by the General Permitted Development Order itself, and section 91 does not apply to permission granted by a development order (s91(4)(a)). But some routes carry completion deadlines in the Order itself:
- Additional storeys (Class AA): "the development must be completed within a period of 3 years starting with the date prior approval is granted" (Class AA.2(3)(c)).
- Commercial to residential (Class MA): "Development must be completed within a period of 3 years starting with the prior approval date" (Class MA.2(5)).
- Agricultural buildings to homes (Class Q): the same 3 years from the prior approval date (Class Q.2(4)).
- Larger home extensions (Class A.4): the current text of Class A contains no completion deadline (Class A). The old completion paragraphs, A.4(13)–(15), were omitted from 25 May 2019 by SI 2019/907 (see the amendment notes on Class A).
An article 4 direction can withdraw permitted development rights in an area, but it does not affect prior-approval development where the prior approval date was before the direction came into force and the development is completed within 3 years of the prior approval date (GPDO art 4(2)(a)). Permitted development under Part 1 is a separate question from expiry; see permitted development rights explained.
What counts as starting work?
For the purposes of sections 91 and 92, "development shall be taken to be begun on the earliest date on which any material operation comprised in the development begins to be carried out" (s56(2)–(3)). A "material operation" is (in s56(4)):
- any work of construction in the course of the erection of a building;
- any work of demolition of a building;
- the digging of a trench which is to contain the foundations, or part of the foundations, of a building;
- the laying of any underground main or pipe to the foundations, or part of the foundations, of a building, or to such a trench;
- any operation in the course of laying out or constructing a road or part of a road; and
- any change in the use of land that constitutes "material development" (defined in s56(5)).
Examples that usually count, if lawful: digging foundation trenches for the approved building, or demolishing a building that the permission covers. On the wording of s56(4), clearing vegetation or putting up a site hoarding is unlikely to count on its own, because neither is on the list. Very minor works are a common subject of dispute, so take advice before relying on them.
The pre-commencement conditions trap. Many permissions say "no development shall take place until" something is approved, such as a drainage scheme or materials. The Planning Practice Guidance says development carried out without complying with a pre-commencement condition "would be unlawful and may be the subject of enforcement action" (PPG Use of planning conditions 21a-007). The courts apply this to the question of whether the permission was implemented in time: in Whitley the Court of Appeal held that operations that contravene the conditions "cannot be properly described as commencing the development authorised by the permission" (F G Whitley & Sons v Secretary of State for Wales [1992] 3 PLR 72, quoted in Hart Aggregates v Hartlepool BC [2005] EWHC 840 (Admin)). That means digging one trench does not always keep a permission alive. The principle has limits: the High Court in Hart Aggregates described it as a judicial creation that should not be applied so rigidly that it produces "absurd and wholly unforeseen results" (paras 42–43), and it quoted the Court of Appeal in Prokopp (at [83]) recognising an exception where enforcement action against the breach of condition would not be possible (Hart Aggregates, para 87). Whether a given start counts is fact-sensitive and a common subject of disputes, so do not rely on a general answer.
Evidencing your start. Keep dated photographs, invoices and any site-visit correspondence, and keep the decision notice and discharge-of-conditions decisions with them. These are practical steps, not statutory requirements.
Using a certificate to confirm a lawful start. A certificate of lawfulness of existing use or development lets you ask the council whether "operations which have been carried out" are lawful (TCPA s191(1)(b)), and a certificate is conclusive once granted (s191(6)). The applicant must provide evidence that is "sufficiently precise and unambiguous" on the balance of probability (PPG Lawful development certificates 17c-006). For existing development the fee equals the planning fee, £548 for a householder extension from 1 April 2026 (MHCLG fee schedule). Whether a council will certify that a particular start amounts to lawful commencement is for it to decide on the evidence, so check before paying. See lawful development certificates.
Can an expired permission be extended or renewed?
Not by a section 73 application in England. You may read that you can extend a permission with a section 73 variation. The Act says otherwise: planning permission "must not be granted under this section for the development of land in England to the extent that it has effect to change a condition … by extending the time within which (a) a development must be started; (b) an application for approval of reserved matters … must be made" (s73(5)). The Planning Practice Guidance says the same (PPG Flexible options 17a-014). Section 73 also does not apply at all if the time limit "has expired without the development having been begun" (s73(4)). A section 73 permission is a new, independent permission, and the time-limit condition has to remain as in the original (PPG 17a-015).
What you do instead. If you have not begun in time, you need a fresh planning application and a new fee. It is decided on the policies in force when it is decided, not on those of the day of the original decision. The current NPPF was published on 17 August 2026 and its policies are "material considerations which must be taken into account in decision-making from the day of its publication" (NPPF Annex A, para 1; NPPF publication page). A scheme that was acceptable three years ago may not be today. If you have begun lawfully, there is nothing to renew.
If you only need to change a detail, see section 73 applications and non-material amendments.
Completion notices: stalled developments
A council can serve a completion notice where development has been started in time but "will not be completed within a reasonable period". The notice must give at least 12 months, and it takes effect only once the Secretary of State confirms it (TCPA ss94–96; PPG paras 17b-069 to 17b-072). The Levelling-up and Regeneration Act 2023 will replace this in England with new sections 93H to 93J, which include an appeal to the Secretary of State (LURA 2023 s112). As at October 2026 those provisions are in force only so far as they allow regulations to be made (LURA 2023 s255(3); MHCLG progress note), so the existing procedure still applies. legislation.gov.uk already shows sections 94 to 96 with the words "in Wales", which is amended text that has not yet been brought into force for England.
Does planning permission go with the house?
Yes, normally. A grant of planning permission "shall (except in so far as the permission otherwise provides) enure for the benefit of the land and of all persons for the time being interested in it" (TCPA s75(1)). The Planning Practice Guidance says: "Planning permission usually runs with the land and it is rarely appropriate to provide otherwise" (PPG 21a-015).
- Personal permissions are the exception. A permission can be limited to a particular person or class of people, for example an agricultural worker, where there is exceptional need (PPG 21a-015). Read the conditions.
- Conditions come with it. Whoever carries out the development must comply with its conditions, including any time limit and any pre-commencement conditions that remain undischarged.
- Planning obligations bind successors. A section 106 obligation is enforceable "against the person entering into the obligation; and against any person deriving title from that person" (s106(3)).
- Check it is still live. A buyer of land with permission should check whether it has been implemented, whether any time-limit condition has expired, and which pre-commencement conditions are discharged. The expiry date, not the sale, is what ends a permission. See what happens after planning permission is approved and discharge of planning conditions.
What neighbours and buyers should check
Old permissions can surprise neighbours because the consultation happened years earlier. If work starts, find the decision notice and check:
- the date of the decision and the time-limit condition;
- whether pre-commencement conditions were discharged before work began;
- whether a later section 73 permission or non-material amendment has changed the plans;
- whether the work now happening matches the approved drawings.
You can find approved drawings through our guide to how to find approved planning drawings, and see how to read the decision notice and planning conditions. If a permission was never lawfully started in time, the owner needs a new one; if it was, it may still be completed. Enforcement turns on the facts: see planning enforcement.
Wales, Scotland and Northern Ireland
Everything above is England. The periods differ:
| Nation | Ordinary permission | Outline or in principle | Law |
|---|---|---|---|
| Wales | 5 years | Reserved matters within 3 years; start within 5 years of the grant or, if later, 2 years from the final reserved matters approval | TCPA s91(5)(b), s92(2)(c) |
| Scotland | 3 years, after which the permission lapses if development has not begun | Planning permission in principle: 5 years | TCP(S)A 1997 s58, s59(2A) |
| Northern Ireland | 5 years | Reserved matters within 3 years; start by the later of 5 years from the grant or 2 years from the final approval | Planning Act (NI) 2011 s61, s62 |
The England-only rule in s73(5) is expressed to apply to land in England; do not assume the same position in Wales without checking the Welsh text. Wales is moving to the consolidated Planning (Wales) Act 2026, which the Welsh Government expects to commence around October 2027, with the existing law applying until then (Welsh Government).
The point to remember
Three years from the decision date is the default in England, but the decision notice decides. What counts is a lawful start, not a finished building. An expired permission cannot be extended by section 73, so you need a new application. And the permission belongs to the land, so a buyer gets it, and gets its conditions, unless it is a personal permission.
This guide is general information, as at October 2026, and not legal advice. Whether a development has been lawfully begun depends on the facts, the conditions and the evidence.
Frequently Asked Questions
How long does planning permission last in England?
Three years from the date it is granted, unless the decision notice sets a different period. The development must be begun within that time (Town and Country Planning Act 1990 s91). Outline permission is different: reserved matters must be applied for within 3 years, and development must then begin within 2 years of the final reserved matters approval (s92). Read the time-limit condition on your decision notice, because the council can set a shorter or longer period.
Does the work have to be finished before the planning permission expires?
No. For ordinary permissions the test is whether development was begun in time, not whether it was finished. Development counts as begun on the earliest date a 'material operation' starts, such as digging a trench for foundations or building work for a new building (s56). If a development is started and then stalls, a completion notice may be possible (see below).
What counts as starting work on planning permission?
Under section 56(4) of the 1990 Act a material operation is any work of construction in the course of erecting a building, any work of demolition of a building, digging a trench which is to contain the foundations of a building, laying an underground main or pipe to those foundations or trench, any operation in laying out or constructing a road, or a material change of use. The work must be lawful and in line with the permission and its conditions, so a start made before a pre-commencement condition was discharged can fail.
Planning permission has expired. Can I renew or extend it?
Not in England by a section 73 application, which cannot extend the time within which development must be started (s73(5); PPG Flexible options 17a-014). If the permission has lapsed without development having begun, you need a fresh application, which is decided on the policies in force at the time, including the NPPF published on 17 August 2026.
Does planning permission transfer to a new owner?
Yes, normally. Section 75(1) says a grant of planning permission enures for the benefit of the land and of all persons for the time being interested in it, unless the permission says otherwise. Conditions come with it, and planning obligations are enforceable against people deriving title from the original party (s106(3)). Personal permissions are the exception.
How long does outline planning permission last?
In England, an application for approval of reserved matters must normally be made within 3 years of the outline grant, and the development must begin within 2 years of the final reserved matters approval (s92(2)). The council may set different periods (s92(4)). Since 18 February 2026 a court challenge can extend the periods (s92A).
How long does listed building consent last?
Three years from the grant, unless the consent sets another period (Planning (Listed Buildings and Conservation Areas) Act 1990 s18). Works to a listed building without consent are a criminal offence.
Do permitted development rights expire?
Householder extension rights under Part 1 Class A carry no start deadline in the Order, but prior approval routes do carry completion deadlines: for example 3 years from prior approval for additional storeys (Class AA), commercial to residential (Class MA) and agricultural conversions (Class Q). Rights can also be withdrawn for an area by an article 4 direction.
Where is the planning expiry date shown?
On the decision notice, as a time-limit condition, usually near the start of the conditions list, for example 'The development hereby permitted shall begin not later than three years from the date of this permission'. A portal summary may show the received, validated, target or decision date but not the expiry date. If there is no such condition, the statutory three-year period applies (s91(3)).
Disclaimer: PlanWatch provides general information about UK planning processes. This content is not legal advice. Planning law is complex and varies by local authority. Consult a qualified planning consultant or solicitor for advice specific to your situation.